Can new floors be installed in phases instead of all at once?
The plan was to replace the laminate in the bedrooms and hallways without opening up anything else — and the tile sitting underneath the laminate stayed exactly where it was. Laminate is often installed over an older floor, and pulling only the laminate layer keeps the removal simple and avoids disturbing what lies beneath.
Phase 1 covered about 650 square feet — the primary bedroom, two additional bedrooms, and the hallways — with Karndean Opus Rubra gluedown luxury vinyl plank installed in one workday. Running one product through the bedrooms and hallways gives the completed phase a continuous look while the rest of the house waits.
Phase 1 covered the bedrooms and hallways; the basement, kitchen, and living room are planned for Phase 2, completing the whole-home plan in two stages.
Project overview
The goal, materials, and finished scope.
These homeowners wanted brand-new floors for the first home they are building a life in together. In August 2026, Floors Now completed the first of two planned phases by removing laminate from the primary bedroom, two additional bedrooms, and the hallways while leaving the tile beneath in place. The crew installed approximately 650 square feet of Karndean Opus Rubra WP316 gluedown luxury vinyl plank in one workday. The basement, kitchen, and living room remain planned for Phase 2, and this project record can be updated when that work is complete.
Project facts
Completed
August 2026
Documented scope
Residential phased gluedown LVP installation
Property type
Residential Home
Rooms
Primary bedroom, two additional bedrooms, and hallways
Flooring
Karndean Opus Rubra WP316 gluedown luxury vinyl plank
Project goal
Give the homeowners brand-new floors in their first home together, beginning with the bedrooms and hallways
Project photography
The finished result.
Each image and caption identifies the portion of the verified project that is actually shown.
View 1.Completed Karndean Opus Rubra flooring in one of the bedrooms included in Phase 1.
View 2.Phase 1 connected three bedrooms and the hallways with the same warm wood-look LVP.
Scope of work
What we did, step by step.
Phase 1 replaced laminate with gluedown LVP while leaving the tile beneath undisturbed.
1Removed the existing laminate from the three bedrooms and hallways included in Phase 1
2Left the tile beneath the removed laminate in place
3Installed approximately 650 square feet of Karndean Opus Rubra WP316 gluedown luxury vinyl plank
4Completed Phase 1 in one workday, with the basement, kitchen, and living room planned for Phase 2
Common questions
Questions homeowners ask about this kind of project.
What was underneath the laminate that was removed?
Existing tile. We removed the laminate from the three bedrooms and hallways and left the tile beneath in place, then installed the new gluedown LVP over the prepared assembly.
How much flooring was installed in Phase 1?
About 650 square feet of Karndean Opus Rubra WP316 gluedown luxury vinyl plank, covering the primary bedroom, two additional bedrooms, and the hallways.
How long did Phase 1 take?
One workday. The laminate removal, the preparation over the tile left in place, and the gluedown installation across the bedrooms and hallways were all completed in a single day.
What is planned for Phase 2?
The basement, kitchen, and living room. The project record can be updated when that work is complete.
Products and planning
Planning a similar flooring project?
Use these resources to compare the materials, preparation, and installation services involved in this project.
Learn when Luxury Vinyl uses attached padding, separate underlayment, a moisture layer, adhesive, or no added layer—and why the product instructions decide.
Compare waterproof hardwood, Luxury Vinyl, laminate, tile, and other water-resistant flooring claims without confusing the floor with a watertight room.
Tell us about your rooms, flooring, and project goals.
Share the location, rooms, existing floors, materials you are considering, known preparation needs, and timing. Floors Now will review the details and follow up about the most practical next step.