774 sq. ft. of carpet and pad plus 405 sq. ft. of rubber tiles; quantities include cuts and waste
Elapsed work time
One workday in one visit
The problem
Can a basement get new carpet and gym flooring in one visit?
This Colchester basement needed two kinds of flooring at once: comfortable carpet across the finished living areas and both staircases, and a dedicated surface for the home gym. The crew removed and disposed of 866 square feet of old carpet first. Rubber gym flooring takes a different kind of abuse than carpet — dropped weights, shifted equipment, and constant foot traffic — so the gym got 405 square feet of Advanced Edge Sports Flooring AE400 interlocking rubber tiles in Back in Black, fitted to the planned room edges.
The stairs added their own challenge: 27 steps across two staircases — 13 basement stairs and 14 main stairs — all carpeted in the waterfall style, where the carpet flows over each step nose and down the riser in one continuous piece. New Madoc carpet in Coracle went down with new pad throughout the carpeted scope, and the crew moved and worked around the gym equipment as the installation progressed.
Everything was coordinated as the flooring portion of a larger restoration-company project while other renovation work continued. The verified finish work — 40 linear feet of tack strip, 25 linear feet of vinyl transition, metal details, and 30 linear feet of baseboard removed and reset — was completed in the same single visit, so the full flooring scope was done in one workday.
Project overview
The goal, materials, and finished scope.
In August 2026, Floors Now completed the flooring portion of a Colchester basement restoration in one workday and one visit. The crew removed and disposed of 866 square feet of old carpet, installed Madoc carpet in the official Coracle color with new pad throughout the planned basement areas, and carpeted both staircases in the waterfall style for a total of 27 stairs. The supplied carpet-and-pad quantities were 654 square feet for the basement and basement staircase plus 120 square feet for the main staircase; those figures include cuts and waste. The verified finish work included 40 linear feet of tack strip, 25 linear feet of vinyl transition, 3 linear feet of flat silver metal, 3 linear feet of pin metal, and removal and reset of 30 linear feet of baseboard. In the gym, the team installed 405 square feet of Advanced Edge Sports Flooring AE400 interlocking rubber tiles in the official Back in Black color, also including cuts and waste. The tiles were interlocked without adhesive over the older underlayment already in place; no new underlayment or patching was installed. The installers moved and worked around gym equipment as the one-visit installation progressed.
Project facts
Completed
August 2026
Documented scope
Residential basement carpet, stair carpet, and rubber gym flooring installation within a restoration project
Property type
Residential Home
Customer type
Restoration Company
Rooms
Finished basement, basement staircase, main staircase, and home gym
Flooring
Madoc carpet in Coracle with new pad; Advanced Edge Sports Flooring AE400 interlocking rubber tiles in Back in Black
Project goal
Complete the carpet and home-gym flooring portion of a basement restoration while coordinating around gym equipment
Project photography
The finished result.
Each image and caption identifies the portion of the verified project that is actually shown.
View 1.Finished Madoc Coracle carpet on the basement staircase, with the carpeted basement area to the right and interlocking AE400 rubber gym flooring to the left.
View 2.The completed Coracle carpet continues through the restored basement passage and adjoining carpeted areas.
View 3.The last approved view shows the finished carpet and Back in Black AE400 rubber zones immediately after installation while the couch, protective plastic, and gym equipment were still being moved into place.
Scope of work
What we did, step by step.
A one-visit basement restoration scope joined new carpet, two waterfall staircases, and interlocking rubber gym flooring.
1Coordinated the flooring work as part of a restoration-company partnership project
2Removed and disposed of 866 square feet of old carpet across the two listed removal areas: 498 and 368 square feet
3Installed 654 square feet of Madoc carpet in the official Coracle color for the planned basement and basement-stair scope
4Installed another 120 square feet of Madoc Coracle carpet for the main staircase; the carpet quantities include cuts and waste
5Installed new carpet pad throughout the complete carpeted scope
6Completed 27 waterfall-style carpeted stairs: 13 basement stairs and 14 main stairs
7Installed 40 linear feet of tack strip and 25 linear feet of vinyl transition
8Installed 3 linear feet of flat silver metal and 3 linear feet of pin metal
9Removed and reset 30 linear feet of baseboard molding
10Installed 405 square feet of Advanced Edge Sports Flooring AE400 interlocking tiles in Back in Black to the planned room edges; the quantity includes cuts and waste
11Interlocked the rubber tiles without adhesive over the older existing underlayment; no new underlayment or patching was installed
12Moved and worked around gym equipment while completing the installation in one workday and one visit
Common questions
Questions homeowners ask about this kind of project.
What is a waterfall stair installation?
With the waterfall method, the carpet flows over each step nose and continues down the riser in one unbroken piece. All 27 stairs on this project — 13 basement stairs and 14 main stairs — were carpeted waterfall style.
Why does a home gym get rubber flooring instead of carpet?
Gym flooring takes dropped weights, shifting equipment, and hard use that carpet isn't built for. This gym received 405 square feet of Advanced Edge Sports Flooring AE400 interlocking rubber tiles in the official Back in Black color, fitted to the planned room edges, while the basement living areas kept Madoc carpet.
Can you install flooring around gym equipment?
Yes. The installers moved and worked around the gym equipment while the one-visit installation progressed, and the full scope — removal, carpet, both staircases, rubber flooring, transitions, and baseboard reset — was completed in one workday.
Do you install new carpet pad with replacement carpet?
We did here. New carpet pad went in throughout the complete carpeted scope, along with 40 linear feet of tack strip, 25 linear feet of vinyl transition, flat silver and pin metal details, and 30 linear feet of baseboard removed and reset.
Products and planning
Planning a similar flooring project?
Use these resources to compare the materials, preparation, and installation services involved in this project.
Tell us about your rooms, flooring, and project goals.
Share the location, rooms, existing floors, materials you are considering, known preparation needs, and timing. Floors Now will review the details and follow up about the most practical next step.