Verified flooring case study • West Hartford, CT • Completed August 2026

Red Oak Hardwood for Living and Family Rooms

Replace carpet with genuine hardwood and finish both rooms before the homeowners left for vacation

Residential Project · Residential Home

405 sq. ft. solid red oakAfter-hours acclimation deliveryOne-day installation
Engagement
Residential Project · Residential Home
Installed area
405 square feet installed; approximately 425 square feet ordered including waste
Elapsed work time
One workday

The problem

Can two rooms get new hardwood before a vacation?

The homeowners wanted the carpet out of their living room and family room and genuine hardwood in its place — with a firm deadline: the work had to finish before they left for vacation. Solid hardwood complicates a tight schedule because it needs to acclimate inside the home first. Wood adjusts to the indoor temperature and humidity before installation; skip that step and boards can shrink or expand after they're nailed down.

They had considered LVP but chose Somerset High Gloss Collection Natural Red Oak solid hardwood because they preferred the appearance of genuine wood. To protect the three-day acclimation window, a Floors Now team member delivered the material at 9 p.m. after the normal workday so the clock could start immediately.

With acclimation handled, the installation itself was the straightforward part: the crew removed and disposed of 367 square feet of carpet and padding, confirmed the exposed plywood subfloor was in good condition and needed no modification, removed and reinstalled 70 linear feet of baseboard, and nailed down 405 square feet of solid red oak across both rooms. Both rooms were finished in one day before the homeowners left, which pleasantly surprised them.

Project overview

The goal, materials, and finished scope.

For this August 2026 West Hartford project, the homeowners considered LVP but selected Somerset High Gloss Collection Natural Red Oak solid hardwood because they preferred the appearance of genuine wood. Their upcoming vacation created a firm schedule, and the hardwood still needed three days inside the home before installation. To protect that acclimation window, a Floors Now team member delivered the material at 9 p.m. after the normal workday. The crew then removed 367 square feet of carpet and padding, confirmed the exposed plywood was in good condition without modification, removed and reinstalled 70 linear feet of baseboard, and nailed down 405 square feet of solid red oak across the living room and family room. Both rooms were completed in one day before the homeowners left, which pleasantly surprised them.

Project facts

Completed
August 2026
Documented scope
Residential solid-hardwood carpet replacement
Property type
Residential Home
Rooms
Living room and family room
Flooring
Somerset High Gloss Collection Natural Red Oak solid hardwood
Project goal
Replace carpet with genuine hardwood and finish both rooms before the homeowners left for vacation

Project photography

The finished result.

Each image and caption identifies the portion of the verified project that is actually shown.

Somerset High Gloss Collection Natural Red Oak solid hardwood installed beside a fireplace in a West Hartford family room
View 1.Completed Somerset Natural Red Oak solid hardwood in the West Hartford family room after carpet removal and a three-day acclimation period.
Somerset Natural Red Oak solid hardwood installed across a West Hartford living room with the adjoining family room visible
View 2.The adjoining living and family rooms received approximately 405 square feet of nail-down solid red oak in one day.

Scope of work

What we did, step by step.

A 9 p.m. delivery protected the full acclimation and installation schedule.

  1. Delivered the Somerset solid hardwood at 9 p.m. after the normal workday so the material could acclimate inside the home for three days
  2. Removed and disposed of 367 square feet of existing carpet and padding
  3. Inspected the exposed plywood subfloor and confirmed it was in good condition without modification
  4. Removed and reinstalled 70 linear feet of existing baseboard molding
  5. Nailed down 405 square feet of Somerset High Gloss Collection Natural Red Oak solid hardwood across the living room and family room
  6. Completed both rooms in one day before the homeowners left for vacation

Common questions

Questions homeowners ask about this kind of project.

Why choose solid hardwood over LVP?

It came down to appearance. These homeowners considered LVP but selected Somerset High Gloss Collection Natural Red Oak solid hardwood because they preferred the look of genuine wood. We install both — the right choice depends on the room, the budget, and what you want underfoot.

Why was the hardwood delivered at 9 p.m.?

To protect the acclimation window. The solid hardwood needed three days inside the home before installation, and the homeowners were leaving for vacation, so a team member delivered the material at 9 p.m. after the normal workday to get the clock started immediately.

What happens to the old carpet when hardwood goes in?

It comes out completely. We removed and disposed of 367 square feet of existing carpet and padding, then inspected the exposed plywood subfloor. On this project the plywood was in good condition and needed no modification before the nail-down installation.

Can solid hardwood really be installed in one day?

The installation itself can go quickly once the material is acclimated and the subfloor is ready. Here we nailed down 405 square feet of solid red oak across the living room and family room — including baseboard removal and reinstallation — in one workday.

Products and planning

Planning a similar flooring project?

Use these resources to compare the materials, preparation, and installation services involved in this project.

Flooring Advice

Go deeper on hardwood.

Focused answers for the questions that need more room than a buyer's guide.

Browse all Flooring Advice

Plan a project like this West Hartford installation

Tell us about your rooms, flooring, and project goals.

Share the location, rooms, existing floors, materials you are considering, known preparation needs, and timing. Floors Now will review the details and follow up about the most practical next step.

Step 1 of 2

Project basics

How can we help?

What would you like to do?
What type of project is it?

No measurements or street address needed to get started.

Get a free estimate